Subject: (Item A-5) Resolution 2019-62 Authorizing the Filing of the Notice of Completion (NOC) for the Prop 39 Yr 3-5 Lighting Retrofit Services Project at Bear Creek and McNair High School Project No. 6230-6550
:
Goal D
Enclosure: Resolution 2019-62 Authorizing the Filing of the Notice of Completion (NOC) for the Prop 39 Yr 3-5 Lighting Retrofit Services at Bear Creek and McNair High Schools
File Attachment:
Reso 2019-62 NOC Prop 39 Yr 3-5 Lighting Retro Bear Creek and McNair 6.4.19 ada.pdf
Summary: On August 7, 2018, the Board of Education adopted Resolution 2018-48 awarding a contract to Clear Blue Energy Corporation, in the total amount of $797,448.47. There were no approved change orders. The final contract price is $797,448.47.

All work associated with this project has now been completed. This Action will authorize the acceptance of contract and filing of the NOC for the Prop 39 Yr 3-5 Lighting Retrofit Services at Bear Creek and McNair High Schools Project.
Funding: Funding for this project is from Prop 39 Yr 3-5 California Clean Energy Jobs Act Fund 01 and other funding as needed.
Recommendation: It is recommended that the Board of Education adopt Resolution 2019-62.