Agenda Item
Meeting Date: 9/17/2019 - 7:00 PM
Category: Individual Action on Items Pulled from Consent Agenda A - Routine Business
Type: Action
Subject: (Item A-4) Approval of Construction Project Change Order Approval #1 for the Lodi Middle School Relocatable Project No. 0854-8154 (Mr. Kahn)
:
Enclosure: CO 1 Exh A Lodi Middle School Relocatable Project
CO 1 Exh B Lodi Middle School Relocatable Project
File Attachment:
CO 1 Exh A Lodi Middle School Relocatable Project No. 0854-8154.ada.pdf
CO 1 Exh B Lodi Middle School Relocatable Project 0854-8154.ada.pdf
Summary: A change order is the formal documentation of an authorized change in scope to a construction contract. Approval ratifications are presented for the following project:

Lodi Middle School Relocatable Project
Project No. 0854-8154
Approval #1 $ 7,878.00

All of the change order items within these Approvals have been authorized in the field by the District, as necessary modifications to complete the project, or to meet District requirements, and are submitted at this time for ratification by the Board of Education. The “A” Exhibits describe the details of the changes for all of the subject projects, while the “B” Exhibits summarize cumulative contract changes.
Funding: The net change for the project is summarized above.
Recommendation: It is recommended that the Board of Education approve ratification of the changes itemized in the attached “A” Exhibit. Exhibits describe the details of the changes for all of the subject projects, while “B” Exhibit summarize cumulative contract changes.