Agenda Item
Meeting Date: 11/5/2019 - 7:00 PM
Category: Consent Agenda A - Routine Business
Type: Action
Subject: (Item A-7) Approval of Construction Project Change Order 1 for Prop 39 Yr 3-5 HVAC Replacement DSA Project at Washington Elementary School (Mr. Kahn)
:
Goal D
Enclosure: CO#1 Exhibit A Prop 39 Yr 3-5 HVAC DSA (Washington)-ada
CO#1 Exhibit B Prop 39 Yr 3-5 HVAC DSA (Washington)-ada
File Attachment:
CO 1 Exh A Prop 39 Yr 3-5 HVAC DSA (Washington) 11.5.19-ada.pdf
CO 1 Exh B Prop 39 Yr 3-5 HVAC DSA (Washington) 11.5.19-ada.pdf
Summary: A change order is the formal documentation of an authorized change in scope to a construction contract. Approval ratifications are presented for the following project:

Prop 39 YR 3-5 HVAC Replacement DSA Project (Washington)
Project No. 8150-5830
Approval #1 $73,525.70

All of the change order items within these Approvals have been authorized in the field by the District, as necessary modifications to complete the project, or to meet District requirements, and are submitted at this time for ratification by the Board of Education. The “A” Exhibits describe the details of the changes for all of the subject projects, while the “B” Exhibits summarize cumulative contract changes.
Funding: The net change for the project is summarized above.
Recommendation: It is recommended that the Board of Education approve ratification of the changes itemized in the attached “A” Exhibit. Exhibits describe the details of the changes for all of the subject projects, while “B” Exhibit summarize cumulative contract changes.